Project Summary

Bored pile foundation for a 14-story residential tower in BSD, South Tangerang. Completed in 45 days using a combination of hydraulic and rotary rigs, on schedule.

Challenges

  • Site sandwiched between existing buildings → low-vibration required
  • Soft soil in the top 8 m
  • Tight 45 calendar-day schedule

Approach

  • Temporary casing for borehole stability
  • Slump test on every concrete batch
  • 2-shift crew with daily documentation
  • 100% PIT on all piles